7 OF 24 builds have shipped so farAnyone has truck shipped?
Sponsored
7 OF 24 builds have shipped so farAnyone has truck shipped?
Yes my truck was shipped via rail (despite having convoy on sticker). It was near Philadelphia this morning on its way to NYAnyone has truck shipped?
I hear you. I am blend 8/3, tear tag 8/4 or 8/5. Still doesn’t show built on 8/26 so 21-23 days. I don’t have spray in either. Not sure if the platinums are slower? I keep hoping it will magically show up without missing the seat upgradesI've been waiting for built status for what seems like eternity. :-(
Looking at @TaxmanHog 's order tracker (using only orders with build dates)
- For all orders production to build date average duration is 18.76
- all blend dates after 07/01 production to build average duration is 15.54 days
- Production to built duration for all Lariats is 19.87 days
- Production to built duration for all Lariats with blend dates after 07/01 is 16 days
So no massive difference in Lariats
- Longest production to build date post 07/01 is 29 and shortest is 2
Only one order with an August blend date has a production to built duration of more than 20 days.
Only 13 orders with a blend date before mine (08/07) are still not built.
4 are not yet in production which may just be missing data (I am not sure how you put order data into the tracker?)
Trend seems to be going down as you would expect as the production line gets more efficient but I'm on day 19 and still not built.
I'm trying to figure out what options on my order is causing the extra time. Only thing I can see on the forum is spray in liner? Colour and trim doesn't seem to have any trend nor does tow packages.
Nice tracker BTW
OK I am not that far above average duration but still frustrating.
I'm blend 8/3, tear tag 8/3. Still not showing as built. ETA has shifted from delivery on the 26th (today), to the 22nd (Monday of this week), to (as of this morning) Sept. 23.I hear you. I am blend 8/3, tear tag 8/4 or 8/5. Still doesn’t show built on 8/26 so 21-23 days. I don’t have spray in either. Not sure if the platinums are slower? I keep hoping it will magically show up without missing the seat upgrades
Have you chatted with Ford or asked your dealer for location/ETA? I have a Platinum with spray in that has a 8/23 production date (8/18 blend) that I have been told is in the departure lot with a 8/29-9/4 delivery windowI hear you. I am blend 8/3, tear tag 8/4 or 8/5. Still doesn’t show built on 8/26 so 21-23 days. I don’t have spray in either. Not sure if the platinums are slower? I keep hoping it will magically show up without missing the seat upgrades
Just found out it’s at Ramp 51. Now it has a 9/8 delivery date per the dealer. Rail to atl and convoy to our town. Should I be concerned about ramp 51?Have you chatted with Ford or asked your dealer for location/ETA? I have a Platinum with spray in that has a 8/23 production date (8/18 blend) that I have been told is in the departure lot with a 8/29-9/4 delivery window
Rail, most states have delivery first by rail then convoy once closerDo you know if Ford use rail or truck to deliver Lightning to California?
No that I am aware of. That’s their departure lot for trucks to be loaded and shipped out. Not sure what delays look like right now out of that lot, if there are delays. I am sure the eta will change though. Mine says I get my truck next week, I’m not buying that.Just found out it’s at Ramp 51. Now it has a 9/8 delivery date per the dealer. Rail to atl and convoy to our town. Should I be concerned about ramp 51?
Please mark me as shipped as well (8/26). Estimated delivery date range of 9/7 - 9/13.7 OF 24 builds have shipped so far