1. July 9th - Took Delivery of F-150 Lightning
2. July 11th - Applied for CVRP ($2000 State Rebate)
3. July 25th - Received Plates/Reg
4. July 27th - Mailed HOV Decal application
5. July 27th - Switched 91 express Lanes to Special Access (EV)
6. August 1st - Received CVRP email stating 61 days to process from July 25th.
7. August 26 - CVRP Approved Email Received
8. August 31- DMV Lost HOV Application
9. September 6th- Mailed HOV Application
10. September 9th- HOV Decal Check cashed
11. September 22nd- CVRP Check Mailed out
12. September 24th- CVRP Check Received
13. September 26th- HOV Stickers Received
Apparently we should be able to apply for the HOV Decals with Temp Reg but I waited just to make sure.
1. July 9th - Took Delivery of F-150 Lightning
2. July 11th - Applied for CVRP ($2000 State Rebate)
3. July 25th - Received Plates/Reg
4. July 27th - Mailed HOV Decal application
5. July 27th - Switched 91 express Lanes to Special Access (EV)
6. August 1st - Received CVRP email stating 61 days to process from July 25th.
7. August 26 - CVRP Approved Email Received
8. August 31- DMV Lost HOV Application
9. September 6th- Mailed HOV Application
10. September 9th- HOV Decal Check cashed
11. September 22nd- CVRP Check Mailed out
12. September 24th- CVRP Check Received
13. September 26th- HOV Stickers Received
Apparently we should be able to apply for the HOV Decals with Temp Reg but I waited just to make sure.