So what's the shakedown period for a plant like this 6 months +-. Or is this Fords first plant of this type so 9 months?
PPAP builds are scheduled through February. Job1 is scheduled for April-ish. Management seems to be taking it slow, but this plant is unlike any other in the Ford system. The level of automation, and the proximity to the workforce, are different than any plant I know about.

All the dates I know are preliminary. Things could change due to part availability or supplier issues.
Sponsored

 

jbirdzee

Well-known member
Joined
Jun 20, 2021
Threads
2
Messages
50
Reaction score
42
Location
NY
Vehicles
23 Lightning Pro ER
Occupation
Engineer
PPAP builds are scheduled through February. Job1 is scheduled for April-ish. Management seems to be taking it slow, but this plant is unlike any other in the Ford system. The level of automation, and the proximity to the workforce, are different than any plant I know about.

All the dates I know are preliminary. Things could change due to part availability or supplier issues.
Please forgive my ignorance - but what is a "PPAP" build?
 

Pioneer74

Well-known member
Joined
Aug 16, 2021
Threads
33
Messages
3,620
Reaction score
6,488
Location
Dearborn
Vehicles
2022 Lightning Lariat ER - 2022 Mach-E Premium
Occupation
Electrician
Please forgive my ignorance - but what is a "PPAP" build?
Part Production Approval Process. It consists of builds that will be used for crash tests, EPA certification and testing. They will all be scrapped as they are not sellable.
 
 