Now that I have a 6/6 build date, it's time to get the plans off the drawing board and implement.
Plan 1, second 200 amp service drop to our stand-alone garage, 200 amp LC with circuit for the Ford Charger Pro and the rest of garage loads move to the new panel, then remove existing 2 x 15amp wiring coming from the house.
Plan 2, if the utility refuses to allow a second service drop to our property, then we need a 100 to 400 upgrade on our house feed line, all new service entrance on the house, 200 amp upgrade inside the house, then a 200 amp second tap (through an external in cabinet 200 amp breaker) to new underground conduit from house to garage, then another 200 amp load center in the garage, servicing all garage loads and the new Ford Charger Pro.
Either way is going to cost a lot and absorb the value of my federal credit!
Anyone else out there considering a second service drop?
Plan 1, second 200 amp service drop to our stand-alone garage, 200 amp LC with circuit for the Ford Charger Pro and the rest of garage loads move to the new panel, then remove existing 2 x 15amp wiring coming from the house.
Plan 2, if the utility refuses to allow a second service drop to our property, then we need a 100 to 400 upgrade on our house feed line, all new service entrance on the house, 200 amp upgrade inside the house, then a 200 amp second tap (through an external in cabinet 200 amp breaker) to new underground conduit from house to garage, then another 200 amp load center in the garage, servicing all garage loads and the new Ford Charger Pro.
Either way is going to cost a lot and absorb the value of my federal credit!
Anyone else out there considering a second service drop?