Now that we've made it through all of the steps of the Lightning rollout I've compared the actual dates to the predicted dates that were based on the Mach E. Happily, Ford met or exceeded the timeline they had for the Mach E rollout.
14 April 2022-EPA ranges released (actually 14 March )
18 April 2022-First retail order build date (actually around 21 April, although some unconfirmed reports of earlier builds. Some fleet orders documented as early as 15 March)
1 May 2022-"First impressions (no driving impressions)" media embargo lifted (actually 2 May)
6 May 2022-"First drive" media embargo lifted (actually 11 May)
22 May 2022-First retail order delivery (actually 26 May)
11 June 2022-First FCTP (mannequin) deliveries (actually 25 May)
14 April 2022-EPA ranges released (actually 14 March )
18 April 2022-First retail order build date (actually around 21 April, although some unconfirmed reports of earlier builds. Some fleet orders documented as early as 15 March)
1 May 2022-"First impressions (no driving impressions)" media embargo lifted (actually 2 May)
6 May 2022-"First drive" media embargo lifted (actually 11 May)
22 May 2022-First retail order delivery (actually 26 May)
11 June 2022-First FCTP (mannequin) deliveries (actually 25 May)